Designed by ATP/amd.sigma in record time
Planner team: ATP architects engineers/amd.sigma strategic airport development
Design start: 12/2017, Completion and ready for take-off: 09/2020
In 2017, the planner team ATP architects engineers/amd.sigma strategic airport development was commissioned to completely rework the existing concept for the construction of an additional terminal (T2) for six million passengers per year at Berlin Brandenburg Airport (BER). The challenge was to reduce the GFA from 40,000 m² to around 23,000 m² while still being ready for the general opening deadline of October 2020. Today, T2 is “ready for take-off”.
...